Parc Tondu – Llanmoor Developments Progress

January 2026 Update on the Link road at Tondu – You will remember we attended a NHCC meeting, objecting to the request by Llanmoor to delay construction of the link road until 235 homes are occupied, instead of the originally agreed 136 homes. This we did on the principal, should they be allowed to get away with this – then what next!
The Planning Committee deferred the decision to allow new traffic surveys to take place in September 2025, and shock, horror, this was agreed to by a local councillor.
Cllr Tim Thomas has now reported that these traffic surveys have now been completed and reviewed by highway officers.
Amazingly, the Officers have concluded traffic levels are similar to earlier surveys and have supported delaying the link road trigger to 235 homes. Yes, they really believe there is the same amount of traffic – unbelievable!!!!!
Of course, a further 100 dwellings won’t add to the traffic choas that is Tondu, will it???? This means planning approval can now proceed once the developer (Llanmoor) signs a Section 106 legal variation.
Allowing the developer to delay the delivery of the link road has set a precedent. I wonder what will be next.

On 25/4/25 Llanmoor Homes submitted an application to BCBC to change the planning condition so a maximum of 235 homes https://planning.bridgend.gov.uk/Planning/Display/P/25/259/RLX – just over half of the total homes planned at the development – can be completed and occupied before they need to deliver the mini-bypass. 
In the original planning application – detailed plans for which were approved in 2020 – a maximum of 136 homes could be built and occupied before the developers would need to redirect Maesteg Road (“Link Road”) to join the Lidl/Ffordd Antwn roundabout. This would take some pressure off the (notorious) Tondu railway bridge junction. 
Although some site clearance has taken place, work on the mini-bypass stopped a while ago. A traffic analysis carried out to support their application concluded that traffic along Maesteg Road hasn’t changed much since 2014. Additionally, the current road network can cope with the traffic already being generated by the development. 
Llanmoor expects the 235-home limit to be reached in the summer of 2027. They believe 2027 is a “more realistic” timescale to deliver road layout changes.
Closing date for objections is 4/6/25 email planning@bridgend.gov.uk

Concerns over spread of Japanese Knotweed:
On September 19th 2024, we wrote to Llanmoor regarding our concerns over the spread and control of this invasive species:
I am writing to express our concern regarding the ongoing presence and potential spread of Japanese Knotweed at the Parc Tondu development. As you may be aware, this invasive species poses a significant threat to both the environment and property values.
Given the recent clearance efforts in January 2024, residents are keen to understand the specific measures Llanmoor are implementing to control the growth of Japanese Knotweed and prevent its further spread. I would be grateful if you could provide details on the following:
1. Control Methods: What methods are being used to eradicate or contain the existing Japanese Knotweed? Are these methods effective in the long term?
2. Prevention Strategies: What precautions are in place to prevent the accidental spread of Japanese Knotweed by footfall or other means? This could include measures such as footbaths or decontamination procedures.
3. Monitoring and Maintenance: How frequently is the site being monitored for signs of new growth or spread? What maintenance plans are in place to ensure ongoing control?
I believe it is essential to take proactive steps to address this issue before it becomes more widespread. I would appreciate your prompt attention to this matter and look forward to hearing from you soon.
for housing.

Response from Llanmoor:
“We have appointed a specialist invasive species contractor to implement the Japanese Knotweed and Himalyan Balsam eradication works in accordance with the eradication plan approved under Outline Planning Condition 21. 
The general strategy involves several rounds of treatment to weaken the plant and reduce seasonal growth and spread. This will be followed by staged removal of the knotweed initially comprising removal of the tree stumps, cleansing and processing any Japanese Knotweed rhizomes for removal off site, followed by a wholescale excavation of the knotweed in accordance with industry best practices, screening and processing of the soils to remove the Japanese Knotweed rhizomes and any impacted soils. Treatment and monitoring will take place before site wide earthworks are undertaken to prepare the site for housing.
All works will be undertaken by the appointed specialist invasive species contractor who will certify and warranty the works along with a long term monitoring plan.
To date, a number of rounds of treatment have taken place on site, with another round of spraying programmed for next week. The tree stumps removal is due to commence at the end of September and will take approximately 4-weeks to complete. During these works the contractor will establish safe working protocols to minimise the risk of cross contamination of areas unaffected by invasive species growth and off site spread.
Following the removal of the tree stumps, we will proceed with site investigation works
involving trial pits and boreholes to assess the ground conditions on the site.
These investigatory works will also be supervised by the invasive species
contractor to ensure the risk of cross contamination is minimised.
In order to safely manage the ongoing invasive species eradication, site investigation and demolition works we have applied to BCBC to temporarily close Footpath 17 (Ynysawdre) which crosses the site. This will also address the risk of cross contamination by members of the public crossing the site and will additionally ensure that Health & Safety Regulations are complied with.”

Update on works: 11th January 2024

We were alerted to the fact someone had commenced the clearing of the area around the Wood store, off Derllwyn Road and following our seeking further clarification, we have received the following response from Llanmoor:

“We operate within and in accordance with approvals and all and any works on site are permitted. The land is owned and controlled by Llanmoor and we had allow the tenant to operate from the site rent free for some considerable time.
We have now secured sought possession so that the site can be cleared ahead of further necessary ground investigation and archaeology works being carried out, again all approved by both planning and statutory bodies.
On the 17th January works will commence on site in relation to clearance of the trees and undergrowth that is permitted by the permission, and whilst we will be notifying the Council of this by separate means I have included Phil Thomas, Planning Officer above for his information.
Site clearance will be supervised by our ecology consultants, and we have notified the PROW Officer that works will be being carried out near the existing public footpath and appropriate precautions will be being taken to protect the continued use.”

Permitted Areas

Phase 1+ is well under way, with many houses already sold and others reserved. The Sales centre is open – Thursday to Monday 10.30am to 5.00pm or 0333 3208162. Details of houses and the site plan (Phase One+) are available on the Llanmoor website: https://www.llanmoor-homes.com/development/parc-tondu/
Site working hours will be Monday to Friday 8.00am to 5.30pm and Saturdays 8.00am to 1.00pm. Material Deliveries will be restricted to be between 8.00am to 4.00pm.
Out of hours security will be in place and they remind all residents of the dangers of construction sites and ask they do not attempt to access the works area.
Any questions or concerns should be directed to Llanmoor Homes on 01443 228413 or Email: info@llanmoor-homes.co.uk or customercare@llanmoor-homes.co.uk.
After emails to BCBC and Llanmoor, the developers have re-opened access to the cycle path, which will remain open. However, they do however reserve the right to close the path as and when is necessary to ensure users and members of the public are protected at all times.

An issue that might be of interest to members of our Association and the Community in general, is in relation to the adoption and future maintenance of all of the areas of Public Open Space and play Space within the site. BCBC are not willing to take on the maintenance of these areas and as such Llanmoor are looking into the creation of a Management Company, perhaps partly owned by residents, the Community Council, Park Slip Nature Reserve and/or Community Association.